Delay and extension of time
Notices travel up within their time limits, the Engineer decides, the Employer approves, and the result comes back down.
Show steps for
10 steps in this process
1Early warning notice Subcontractor Main Contractor
RB 8.3 Promptly, when a probable future event may delay or disrupt the works
AED 39
2Subcontractor notice of delay and claim Subcontractor Main Contractor
SC 20.2 Within 21 days of awareness, so the main contractor can notify within its own 28 days
AED 59
3Notice of claim Main Contractor Engineer
RB 20.1 Not later than 28 days after awareness of the event, or the claim is lost
AED 59
6Fully detailed extension of time and prolongation claim Main Contractor Engineer
RB 20.1 Within 42 days of awareness of the event
AED 249
7Engineer’s determination Engineer Main Contractor
RB 3.5 The Engineer responds within 42 days of receiving the detailed claim (Sub-Clause 20.1)
AED 79
8Engineer’s recommendation to the Employer (time and cost) Supervision Consultant Employer
RB 8.4
AED 79