Engineer and Main Contractor

Variation proposal with cost and time breakdown

Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 13.3
Time limit
As soon as practicable after the request; particular conditions often set 14 days
Format
Word and ExcelLanguage: English
Stage
Post-contract: 5. Changes and claimsRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Description of the work, programme effect and a priced breakdown at contract rates or dayworks.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 13.3.
  • Time limit: As soon as practicable after the request; particular conditions often set 14 days.
  • Goes with: Variation order
  • Step 5 of 10 in the Variation process.

What you get

Where it sits in the processes

Variation, step 5 of 10View all