Engineer and Main Contractor

Programme review comments

EngineerMain Contractor
Clause
FIDIC 1999 Red BookSub-Clause 8.3
Time limit
Notice within 21 days if the programme does not comply
Format
WordLanguage: English
Stage
Post-contract: 3. Sign and startRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • The Engineer’s notice of the respects in which the programme does not comply with the contract.
  • Sent by the Engineer to the Main Contractor.
  • Written to FIDIC 1999 Red Book, Sub-Clause 8.3.
  • Time limit: Notice within 21 days if the programme does not comply.
  • Goes with: Baseline programme submission

What you get