Notice extending the defects notification period

EngineerMain Contractor
Clause
FIDIC 1999 Red BookSub-Clause 11.3
Time limit
Extension limited to two years in total
Format
WordLanguage: English and Arabic
Stage
Post-contract: 7. Handover and closeRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Extends the period for works or sections that could not be used because of a defect.
  • Sent by the Engineer to the Main Contractor.
  • Written to FIDIC 1999 Red Book, Sub-Clause 11.3.
  • Time limit: Extension limited to two years in total.